Scan the QR code to watch a comprehensive video on how set a Narrow
Pass.
Note: most of the measures required during the process are available on
the RoboRuler.
If the passage is NARROWER than 1.5m and longer then 2m,
dual-square installation shall be completed as follows:
1. Define the entry to the Narrow Pass – the point where the mower
will start driving towards the Sub-Zone.
2. 70 cm (28.5 inches) from the Narrow Pass entry, set a Perimeter
Island (see 2.2.1) as shown in the picture above.
3. Continue to lay the wire along the edge at a proper distance
(depending on the edge type) until returning to the Narrow Pass
entry from the Sub-Zone side.
4. Measure 70cm (28.5 inches) from that point and lay another
Perimeter Island with the same dimensions.
5. After completing setup of the wire in the Sub-Zone, make sure to
leave 14 cm (5.5 inches) between the wire and the islands on the
way back to the Main Zone.
14cm
14cm
32cm
2 Wires under
same peg