14.3 Testing Meter Start-Up with Earthing Contact Plug
– kWh Function (not SECULIFE IP)
Energy consumption meters can be tested for correct start-up
with this function.
Connection L – N
Earthing contact plug
Start Measurement
The meter is tested with the help of an internal load resistor and a
test current of approximately 250 mA. After pressing the start key,
test power is displayed and the meter can be tested for proper
start-up within a period of 5 seconds. The “RUN” pictograph is
displayed.
TN systems: All 3 phase conductors must be tested against N,
one after the other.
In other types of systems, all phase conductors (active conduc-
tors) must be tested against one another.
Note
If minimum power is not reached, the test is either not
started or aborted.
Evaluate Measured Value
The measured value has to be evaluated after measurement has
been completed:
In the event that “NOT OK” is selected, an error is indicated by the
UL/RL LED which lights up red.
The measured value cannot be saved to memory and included in
the test report until it has been evaluated.
Save Measured Value
Special Case
Start-up of energy consumption meters which are connected
between L and L or L and N can be tested with this function.
Connection L – L
2-Pole Adapter
Note
If an earthing contact outlet is not available, you can use
the 2-pole adapter. N must be contacted with the PE test
probe (L2), and then measurement must be started.
If PE is contacted with the PE test probe (L2) during the
meter start-up test, approximately 250 mA flow through
the protective conductor and any upstream RCD is
tripped.
OK
NOT OK
54


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for Gossen Metrawatt PROFITEST MXTRA at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of Gossen Metrawatt PROFITEST MXTRA in the language / languages: English as an attachment in your email.

The manual is 2,28 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of Gossen Metrawatt PROFITEST MXTRA

Gossen Metrawatt PROFITEST MXTRA User Manual - Dutch - 92 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info