We reserve the right to make changes to dimensions and construction 20 Edition 02.09.2015
© Copyright YGNIS AG CH-Ruswil
8. Commissioning the condensing unit
The condensing unit may only be commissioned by a specialist trained on the product.
In order to ensure successful commissioning of the unit, the following points must be guaranteed by the
electrician.
- The unit is installed hydraulically, electrically, on the gas and flue gas side and is ready for commissioning.
With regard to the correct function of the O
2
sensor, it is particularly important to ensure that
- the condensation drain line does not have a double siphon and the line does not sag,
- the unit is electrically connected and integrated so that it will remain connected to the main even when no
heat is required, thereby guaranteeing that the O
2
sensor will be heated.
- A complete equipotential bonding must be guaranteed.
- The boiler room must be clean, free from dust and be able to be locked.
- All material and equipment which does not belong to the boiler room, must be removed.
- A fresh air supply to the boiler room must be ensured when doors are closed.
- The hydraulic system must be purged.
- The connection pressure of the water must be within the range defined in the "Technical data".
- If subsequent supply is necessary, then the water should be slowly fed to the filling and draining pipes in
order to avoid pressure surges.
- A leakage test of the gas line must have been carried out.
- The connection pressure of the gas line at the unit connection must be the value required by the table
"Technical data".
- The connection of the flue gas line to the flue gas pipe must be leak-tight for the flue gas and condensate.
- The internal siphon of the unit in the condensate drain must be filled with water.
- If the condensing unit is supplied with a condensate neutralisation unit, then this must be prepared in
accordance with separate installation and operating instructions.
- It must be possible to provide maximum heating capacity to the heating system for at least 30 minutes, since
the self-calibration of the unit that is running at this time does not allow any interruption.
After ensuring the above-mentioned points, the unit is ready for commissioning by a specialist.
If the above mentioned conditions, guidelines or regulations have not been observed, the specialist can
refuse to commission the PYROGAS VARINO condensing unit. Temporary commissioning of the
condensing unit (e.g. during construction phases) which leaves out certain conditions must be expressly
approved by the manufacturer.
22


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for Ygnis Varino at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of Ygnis Varino in the language / languages: English as an attachment in your email.

The manual is 1,05 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of Ygnis Varino

Ygnis Varino Usermanual and installation guide - German - 30 pages

Ygnis Varino Usermanual and installation guide - Dutch - 30 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info