Commissioning
Greenstar Danesmoor Utility 2022+ and Utility System 2022+ - 6 721 846 263 (2022/01)40
6 Commissioning
6.1 Pre-Commissioning checks - 18/25 Regular shown
1. Check that the service and water pipes are connected correctly.
Check that all unused sockets are capped.
2. Check that the oil supply is Kerosene (Class C2) and that the
pipework is connected correctly to the oil pump via the supplied
flexible oil hose.
Check that the burner is seated correctly on its mounting flange and
that the oil hose/s are routed correctly.
See page 51, figure 90 for correct routing of the oil hose.
Turn on the main oil supply valve at the tank, check the oil supply
pipework and connections. Rectify any leaks.
3. Check the flue is correctly fitted and the connections are secure.
4. Check the condensate pipework is correctly fitted and connected.
Check the condensate trap is filled with water.
Fig. 60 Pre-Commissioning checks
6.2 Filling the system
Open all system and radiator valves.
Turn on the water main stop cock.
Open vented systems only:
Turn on the water to the system feed and expansion cistern and
allow the system to fill.
Sealed systems only:
Check and if required, adjust the expansion vessel pressure using
the Schraeder type valve.
Fill the system to between 1 and 2 bar pressure via a WRAS approved
filling link.
Vent all radiators, retighten when completed.
Monitor the pressure gauge during venting and repressurise if
required.
Check the system and correct any leaks.
Bleed air from at least one of the secondary heat exchanger air vents
(a radiator key is ideal for this). There are two venting bosses [1] on
the top of the secondary heat exchanger. Only one can used if fluing
to the side.
Fig. 61 Manual vent points
[1] Manual vent points (each side of the secondary heat exchanger).
CAUTION: 230 Volts
Isolate the mains electrical supply before starting any
work and observe all relevant safety precautions.
NOTICE: If the boiler is not to be commissioned then:
After successfully completing all of the checks and any
rectification work, close the water valves, shut off the
oil supply and electrically isolate the boiler.
Complete the installation part of the Guarantee
Registration Card, and complete a CD10 or equivalent
to inform the LABC of the installation.
Refit the top panel.
1. 3.
4.
2.
System boiler only
The charge pressure of the built-in 10 litre expansion
vessel is 0.5 bar as supplied, which is equivalent to a
static head of 5 metres. At 1 bar pressure the vessel will
provide 92 litres expansion capacity, the boiler has a
primary water capacity of 20 to 22 litres and therefore
additional system expansion capacity may be required.
If an extra expansion vessel is fitted to the central
heating return, adjust this to the same pressure as
the appliance internal expansion vessel, refer to
separate instructions supplied with the extra
expansion vessel.
6720813284-21.1Wo
1
40


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for Worcester-Bosch Greenstar Danesmoor Utility Regular - Utility System at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of Worcester-Bosch Greenstar Danesmoor Utility Regular - Utility System in the language / languages: English as an attachment in your email.

The manual is 14.85 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info