Commissioning
6720813171 (2016/05) 43
10.2.9 Measuring the flue gases CO
2
emissions
Open at least 2 thermostatic radiator valves. Do not switch on the
boiler.
Push on the control panel to open it ( fig. 68, page 32).
Switch off the heating system by pressing the mains switch of the
BC10 basic controller ( fig. 90, [1]).
Remove the cover from the flue gas measuring point [1].
Connect the flue gas analyser to the left-hand measuring point.
Fig. 91 Measuring the gas supply pressure
Switch on the heating system by pressing the mains switch of the
BC10 basic controller ( fig. 90, [1]).
Press and hold the “Chimney sweep” button ( fig. 90, [3])
(approximately 2 seconds), until the dot in the right-hand bottom
corner of the display ( fig. 90, [9]) appears. See also table 10,
“Flue gas test”, page 34.
After the “Burner” LED ( fig. 90, [6]) has lit up wait for one minute
until the boiler is burning at full load.
Measure the carbon monoxide content at the flue gas measuring
point ( fig. 91).
The CO values in air-free condition must be less than 400 ppm or
0.04 vol. %. Values of 400 ppm or more indicate an incorrect burner
adjustment ( section 10.2.7, page 41), a dirty gas burner or heat
exchanger or burner faults.
You must determine and remove the cause ( chapter 12,
page 46).
Press the “Chimney sweep” button ( fig. 90, [3]) to clear the
reading. See also table 10, “Flue gas test”, page 34.
Switch off the heating system by pressing the mains switch of the
BC10 basic controller ( fig. 90, [1]).
Remove the flue gas analyser and fit the cover back onto the flue gas
measuring point ( fig. 91, [1]).
Switch on the heating system by pressing the mains switch of the
BC10 basic controller ( fig. 90, [1]).
Press on the control panel to close it ( fig. 95, page 45).
10.2.10 Carrying out a function test
During initial start-up and annual inspection and/or needs-oriented
servicing, make sure that all control, regulating and safety devices
are in full working order and, if applicable, check them for correct
adjustment.
The gas and water circuits must be tested for leaks
( sections 10.2.1 and 10.2.8).
10.2.11 Measuring the ionisation current
Push on the control panel to open it ( fig. 68, page 32).
Open at least 2 thermostatic radiator valves. Do not switch on the
boiler.
Switch off the heating system by pressing the mains switch of the
BC10 basic controller (
fig. 90, [1]).
Turn the vent key through a quarter rotation to undo the boiler door
lock ( fig. 71, see detailed picture, page 37).
Push the fastener down and open the boiler door ( fig. 71,
page 37).
Undo the plug and socket connection of the monitoring cable.
Fig. 92 Removing the ionisation electrode plug and socket connection
Connect the multimeter in series. Select the μA DC range on the
multimeter. The multimeter must have a resolution of at least 1 μA.
Fig. 93 Measuring the ionisation current
Switch on the heating system by pressing the mains switch of the
BC10 basic controller ( fig. 90, [1]).
Activate the Service mode in accordance with the “Service mode”
menu ( table 11, page 34).
Set the capacity to minimum (part load) according to the “Service
mode” menu ( table 11, page 34).
After the “Burner” LED ( fig. 90, [6]) has lit up wait for one minute
until the boiler is burning at part load.
6 720 648 726-091.1TD
1
6 720 648 726-092.1TD
6 720 648 726-093.1TD
43


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for Worcester-Bosch GB162-80 at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of Worcester-Bosch GB162-80 in the language / languages: English as an attachment in your email.

The manual is 5,43 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of Worcester-Bosch GB162-80

Worcester-Bosch GB162-80 Installation Guide - English - 12 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info