SMA Solar Technology AG 7 Initial Start-Up
Installation Manual SB13_21TL-IA-en-65 39
7.4 Commissioning the Inverter
Requirements:
The inverter is correctly mounted.
The miniature circuit-breaker is correctly rated and installed.
All cables are correctly connected.
Unused DC inputs are sealed with appropriate DC connectors and sealing plugs.
The country data set is configured according to the country or application.
If an ESS is in use, it is securely plugged in.
☐The inverter is closed.
Procedure:
1. Switch the miniature circuit-breaker on.
2. If an external DC switch-disconnector is installed, switch it on.
The start-up phase begins.
The green LED is lit and the display consecutively shows the device type or designation of
the inverter, the firmware version, and the configured country data set.
Green LED flashing
The DC input voltage is still too low, or the inverter is checking the electricity grid.
Once the DC input voltage is sufficiently high and the grid connection conditions are met,
the inverter starts operation.
Red LED on
The inverter has detected an earth fault or one of the varistors is defective.
Eliminate the error (see Section10.5 "Red LED Permanently On", page54).
Yellow LED flashing
There is probably a fault or disturbance present.
Eliminate the fault or disturbance (see Section10 "Troubleshooting", page45).
3. If the inverter is being commissioned in Italy, start the self-test (see Section7.5 "For Italy Only:
Starting the Self-test", page40)
39


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for SMA Sunny Boy 1600TL at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of SMA Sunny Boy 1600TL in the language / languages: English as an attachment in your email.

The manual is 1,66 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of SMA Sunny Boy 1600TL

SMA Sunny Boy 1600TL User Manual - Dutch - 2 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info