upper section of the chimney (see installation sequence 20a-
20b).
Attention! for all pre-assembled models:
the mounting operations “1, 2, 3” should not be taken into
consideration, for installation begin at operation “4”.
1. Rest the suction unit on a flat surface and thread the lower
part of the hood onto it (consult the figure corresponding
to the model in possession - Fig. 1C/8C - 1D/8D - 1I/8I -
1E/8E - 1F/8F - 1G/8G - 1H/8H - 1R/8R - 1N-1O-1P).
2. Make all the electrical connections between the two parts
(Fig. 9).
3. Permanently fix the cooker hood to the suction group with
the screws (consult the figure corresponding to the model
in possession - Fig. 1C/8C - 1D/8D - 1I/8I - 1E/8E - 1F/8F
- 1G/8G - 1H/8H - 1R/8R - 1N-1O-1P).
4. Using a pencil, draw a line on the wall, extending up to the
ceiling, to mark the centre. This will facilitate installation
(Fig. 10).
5. Rest the drilling template against the wall: the vertical
centre line printed on the drilling template must
correspond to the centre line drawn on the wall, and the
bottom edge of the drilling template must correspond to
the bottom edge of the hood: bear in mind that, when
installation is complete, the underside of the hood must
be at least 50 cm above the cooker top in the case of
electric cookers, and at least 65 cm above the cooker top
in the case of gas or mixed cookers.
6. Place the lower support bracket on the perforation
diagram making it coincide with the traced triangle, mark
the two external holes and perforate. Remove the
perforation diagram, insert two wall-dowels and fix the
support bracket of the hood with two 5x45 mm screws
(Fig. 10).
Attention: only the models illustrated in Fig. 1Q/10Q:
Fix the central bracket with two screws and wall-dowels
above the lower bracket (see perforation diagram for
positioning the holes).
7. If supplied dismantled, fix the hooks to the side of the
aspiration group with two screws (fig. 10a). Hang the
hood onto the lower bracket.
8. Adjust the distance of the hood from the wall.
9. Adjust the horizontal position of the hood.
10. Using a pencil mark the cooker hood permanent drill hole
inside the suction group (1 or 2 fixing points are
necessary for permanent mounting) (Fig. 11).
11. Remove the hood from the lower bracket.
12. Drill at the point marked (Ø8mm) (Fig. 12).
13. Insert 1 or 2 wall screw anchors according to requirement.
14. Apply the flues support bracket „G“ to the wall adherent to
the ceiling, use the flues support bracket as a perforation
diagram (if present, the small slot on the support must
coincide with the line drawn previously on the wall) and
mark two holes with a pencil. Make the holes (Ø8mm),
and insert 2 dowels (Fig. 13).
15. Fix the chimney support bracket to the wall using two
5x45mm screws.
16. Hook the hood onto the bottom bracket.
17. Fix the hood into its final position on the wall
(ABSOLUTELY ESSENTIAL) (Fig. 14).
18. Connect a pipe (pipe and pipe clamps not provided, to be
purchased separately) for discharge of fumes to the
connection ring located over the suction motor unit.
If the hood is to be used in ducting version, the other end
of the pipe must be connected to a device expelling the
fumes to the outside. If the hood is to be used in filter
version, then fix the deflector F to the chimney support
bracket G and connect the other extremity of the pipe to
the connection ring placed on the deflector F (Fig. 13-
15).
19. Connect the electricity.
Attention: only the models illustrated in Fig. 1Q:
Continue from the installation sequence number 23.
20. Apply the chimney stacks and fasten them at the top to
the chimney support „G“ (20b) using 2 screws (20a)
(Fig. 16).
Only for model with optical fibers point lighting (Fig.
1G):
Check that the chimneys may be removed to permit
access to the optical fibers lamp housing area.
Only for the model with control panel on chimney flue
(Fig. 1L- 17):
Insert the command plate from the motor group through
the chimney flue slit from the inside towards the outside
(20c).
Carry out the connection of the control panel to the
command plate.
Attention! The terminal pivot on the plate MUST
correspond to the drill hole on the connection block
situated at the back of the control panel.
21. Slide the bottom section of the chimney down until it
completely covers the suction unit and slots into the
housing provided on top of the hood (Fig. 18).
22. Fix the lower section of the chimney with two screws (only
for the model in Fig. 1H/19H-1J/19J-1L/19L-1M/19M-
1N/19N-1O/19O-1P/19P).
23. Only the models illustrated in Fig. 1Q:
Put the flues unit on the suction unit.
Connect the electricity between the two parts (Fig. 9).
Fix the flue units definitively to the suction unit with the
screws (consult the figure corresponding to the
model in possession) (Fig. 8Q).
Attention! Check that the lower section of the flue fits
onto the central bracket (Fig. 20).
Fix the upper section of the flue units to the flues support
bracket with two screws (Fig. 16).
Remount the carbon filter frame and the fat/s filter/s and check
the perfect functioning of the hood.
11


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for Elica Bridge at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of Elica Bridge in the language / languages: English as an attachment in your email.

The manual is 1,84 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info