2.3 PLACING THE BOILER
The boiler is intended to be installed and operated in the premises with the basic environment
(AA5/AB5) following the STN 33 2000–1:2009–04.
Boiler room must meet also the following conditions:
The boiler room must not be potentially explosive environments, due to the fact that the
boiler is not suitable for use in such environments.
The temperature in the boiler room must not fall below freezing point.
Boiler provides no lighting. The customer must ensure sufficient light source according to
local standards and regulations.
If the boiler will be installed at altitudes over 1 800 m, it is necessary to consulted this instal-
lation with the producer.
The boiler room must be secured with a hole for good air circulation and also required inlet
for combustion air, but at least 200 cm
2
. The hole should be designed so that external
weather does not affect its function (rain, snow, wind).
By the boiler installation it is necessary to keep the safety distance of its surface from
flammable materials according to their degree of flammability:
from materials of the flammability degree B, C1 and C2 200 mm
from materials of the flammability degree C3 400 mm
from materials of the flammability degree not approved 400 mm
Examples of classification of the building materials by their degree of flammability:
degree of flammability A inflammable (bricks, blocks, ceramic tiles, mortar, parging)
degree of flammability B partly flammable (heraklith, lignos, board from basalt felt, novodur)
degree of flammability C1 difficult to ignite (hardwood (oak, beech), plywood, werzalit, hardened paper)
degree of flammability C2 normal combustibility (softwood (pine, spruce), chipboard, solodur)
degree of flammability C3 easily ignited (wood fibre boards, polyurethane, PVC, foam rubber, polystyrene)
The sealing board or protection covering (on the protected item) must exceed the boiler edge
for at least 300 mm. Also other items from flammable materials must be protected in this way, if
they are placed near the boiler and it is not possible to keep the safe distance.
If the boiler stands on a flammable surface, it must be protected by an inflammable, heat insulat-
ing mat, which exceeds the edge on the side of the feeding door and the ash tray door for at
least 100 mm. All materials of the A flammability degree can be used as an inflammable, heat
insulating mat.
The boiler must be placed in a such way ensuring sufficient space of at least 1 m from the front
and 0,5 m from the left (right) and rear side. It is necessary to leave the space of at least 1 m
above the boiler.
This space is necessary for basic operation, maintenance and eventual service of the boiler. It is
not allowed to place the boiler in dwelling premises (including corridors). There must be an
opening for the air inlet for burning of at least 200 cm
2
depending on the boiler output.
ATTENETION: The items from flammable materials must not be laid on the boiler and in
the distance shorter than the permitted (safe) one.
The boiler must be turned off, if there is a danger of fire or explosion due to the work (e.g. work
with painting materials, glues, etc.).
It is not allowed to place the boiler in residential premises (including corridors)!
11


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for ATTACK DPX Combi Pellet at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of ATTACK DPX Combi Pellet in the language / languages: English as an attachment in your email.

The manual is 8.73 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info