7 Commissioning
SMA Solar Technology AG
Operating manual STP3-6-3AV-40-BE-en-12 37
7 Commissioning
7.1 Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure See
1. Commission the inverter. Section7.2, page37
2. Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
Direct connection via WLAN
Direct connection via Ethernet
Connection via WLAN in the local network
Connection via Ethernet in the local network
Section8.1, page43
3. Log into the user interface. Section8.2, page47
4. Select the inverter configuration option. Please note that
the SMAGridGuard code for changing the grid-relevant
parameters must be available after completion of the first
ten feed-in hours or installation assistant (see "Application
for the SMAGridGuard code" available at www.SMA-
Solar.com).
Section7.3, page39
5. Ensure that the country data set has been configured cor-
rectly.
Section8.11, page56
6. For PV systems in Italy or Dubai: Start the self-test. Section7.4, page41
7. Make further inverter settings as needed. Section8, page43
7.2 Commissioning the Inverter
Requirements:
The AC circuit breaker must be correctly rated and mounted.
The inverter must be correctly mounted.
All cables must be correctly connected.
Procedure:
1. Switch on the AC circuit breaker.
37


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for SMA Sunny Tripower 4.0 at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of SMA Sunny Tripower 4.0 in the language / languages: English as an attachment in your email.

The manual is 2,37 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of SMA Sunny Tripower 4.0

SMA Sunny Tripower 4.0 User Manual - German - 104 pages

SMA Sunny Tripower 4.0 User Manual - Dutch - 106 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info