8 Operation
SMA Solar Technology AG
Operating manual SBxx-1AV-41-BE-en-10 57
4. Select [Save and continue] after each step up until the step Configure grid management
service.
5. Make the settings as described in the following.
Setting the connected line conductors
In the tab Feed-in management, select the line conductor to which the inverter is connected
from the drop-down list Connected line conductors.
Making settings for systems with a higher unit (e.g. SunnyHomeManager)
1. Set Feed-in management at the grid-connection point to [Off].
2. Set System control and power limitation to [On].
3. In the drop-down list Operating mode active power, select the entry Active power
limitation P via system control.
4. In the drop-down list Operating mode for absent system control, select the entry Use
fallback setting.
5. In the field Fallback active power P enter the value to which the inverter is to limit its
nominal power in case of a communication failure to the higher unit at the end of the timeout
time.
6. In the field Timeout, enter the time that the inverter is to wait before it limits its nominal power
to the set fallback value.
7. If, in the event of a 0% or 0W specification, the inverter is not permitted to feed small amounts
of active power into the utility grid, select the entry Yes in the drop-down list Grid
disconnection for 0% feeding. This ensures that in the event of a 0% or 0W specification,
the inverter disconnects from the utility grid and does not feed in active power.
Making settings for systems without higher-level unit (e.g.
SunnyHomeManager).
1. Set Feed-in management at the grid-connection point to [On].
2. Enter the total PV array power in the field Nominal PV system power.
3. In the drop-down list Operating mode of active power limitation at the grid-connection
point, select whether active power limitation is to be performed via a fixed specification in
percent or in watts.
4. In the field Set active power limit at the grid-connection point, enter the value to which
the active power at the grid-connection point is to be limited. The value must be set to 0 for
zero export.
5. Set System control and power limitation to [On].
6. For system control and power limitation based on set default values, select the entry Act.
power lim. as % of Pmax or Active power limitation P in W and enter the respective
default value.
7. If the inverter itself is to limit the active power limitation to the grid-connection point, perform
the following steps:
In the dropdown list Operating mode Active power, select Act. power lim. via PV
system ctrl.
57


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for SMA Sunny Boy 6.0 at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of SMA Sunny Boy 6.0 in the language / languages: English as an attachment in your email.

The manual is 2,07 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of SMA Sunny Boy 6.0

SMA Sunny Boy 6.0 Installation Guide - German - 104 pages

SMA Sunny Boy 6.0 User Manual - Dutch - 104 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info