SMA Solar Technology AG Troubleshooting
Installation Guide SB11_12_17-IEN100132 37
The approximate position of the ground fault can be determined from the ratio of the measured
voltages between plus against ground potential and minus against ground potential.
Example:
The ground fault is between the second and third module in this case.
3. Repeat step 2 for each string.
The table illustrated below shows the various results and corresponding measures.
The ground fault check is finished.
Result Action
☑You have found a ground fault. The installer of the PV generator must
remedy the ground fault in the affected
string before you may reconnect the string
to the Sunny Boy.
•Do not reconnect the faulty string.
Close and commission the Sunny Boy as
described in section 7.2 "Closing the
Sunny Boy" (page33).
☑You have found no ground fault. It is likely that one of the thermally monitored
varistors is defective.
Check the varistors as described in section
9.1.2 "Checking the Function of the
Varistors" (page38).
37


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for SMA Sunny Boy 1100 at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of SMA Sunny Boy 1100 in the language / languages: English as an attachment in your email.

The manual is 2,17 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info