7 Commissioning the Inverter
Requirements:
The inverter must be correctly mounted.
The circuit breaker must be correctly rated.
All cables must be correctly connected.
A computer with a WLAN- or Ethernet interface or a tablet PC or smartphone with a WLAN
interface must be available.
Procedure:
1. Turn the DC load-break switch of the inverter to
position I.
2. Switch on the circuit breaker.
The green LED flashes for approx. 30seconds and then glows permanently or pulses.
Feed-in operation begins.
The green LED is still flashing after one minute?
The DC input voltage is still too low.
Once the DC input voltage is sufficiently high, feed-in operation begins.
The red LED is glowing?
An error has occurred.
Rectify the error (see service manual at www.SMA-Solar.com).
3. Configure the inverter via the user interface (see Section8.1.1 "Calling Up the Inverter User
Interface via Direct Connection", page34). When doing so you can either configure the
inverter manually, use the installation assistant or adopt an existing configuration from a file.
SMA Solar Technology AG recommends configuration with the help of the installation
assistant.
7 Commissioning the Inverter
SMA Solar Technology AG
Operating Manual 33SB15-25-BE-en-10
33


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for SMA Sunny Boy 1.5 at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of SMA Sunny Boy 1.5 in the language / languages: English as an attachment in your email.

The manual is 1,62 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of SMA Sunny Boy 1.5

SMA Sunny Boy 1.5 User Manual - German - 98 pages

SMA Sunny Boy 1.5 User Manual - Dutch - 98 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info