587704
24
Zoom out
Zoom in
Previous page
1/32
Next page
Add refrigerant
The equipment contains
a basic quantity of refrigerant.
Furthermore, for refrigerant line
lengths of more than 5 metres
per circuit, an additional amount
of refrigerant must be added, in
accordance with the following
chart:
ML
262
ML
352
ML
522
Basic
line length
Additional fill quan-
tity
Up to and incl.
5 m
0 g/m
5 m to max.
20 m
30
g/m
30
g/m
30
g/m
After the tightness check has
been successfully completed,
connect the vacuum pump via
the pressure gauge station to
the valve connections on the
outdoor component (see chapter
"Tightness check") and create
a vacuum.
Perform the following checks
prior to putting the unit into
operation for the first time and
after any work on the refrigeration
circuit. Record the results in the
commissioning report:
Check all refrigerant
lines and valves using
leak detection spray or soapy
water for leaks and for
inadvertent reversal of the
suction and injection lines,
with the unit at a standstill.
Check refrigerant
lines and insulation for damage.
Check electrical
connection between
indoor unit and outdoor
component
for correct polarity.
Check that all fastenings,
mountings etc.
are firm and at the correct level.
Before
Commissioning
Make sure that the refrigerant
which is used is always filled
in liquid form!
ATTENTION
NOTE
Check the refrigerant fill
quantity in the event of
overheating
Wear protective clothing when
handling refrigerant.
ATTENTION
Commissioning
Commissioning is only to be
performed and documented
by specially trained personnel.
NOTE
Once all the components have
been connected and tested, the
system can be commissioned.
A functional check should be
performed to verify its correct
function and identify any unusual
operational behaviour prior to
handing it over to the operator.
Function test and test run
Check the following points:
Leak tightness of refrigerant
lines.
Compressor and fan running
smoothly.
In cooling mode, cold air
output by the indoor unit, and
warm air output by the outdoor
component.
Functional test of the indoor
unit and all program sequences.
Check of the surface
temperature of the suction pipe
and determination of vaporiser
overheating. To measure
the temperature, hold the
thermometer to the suction
pipe and subtract the boiling
point temperature reading on
the pressure gauge from the
measured temperature.
Documentation of the
measured temperatures in the
commissioning report.
Check that the stop valves
and valve caps are tight after
carrying out any work on
the refrigerant circuit. Use
appropriate sealant products
as necessary.
NOTE
Functional test for the cooling
and heating modes
1. Remove the caps from the
valves.
2. Begin the commissioning
process by briefly opening the
shut-off valves of the external
unit until the manometer
displays a pressure of approx.
2 bar.
3. Use leak detection spray or
suitable devices to check that all
the connections are leak tight.
REMKO ML...DC - ARCTIC
24
24


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for REMKO ML352 DC at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of REMKO ML352 DC in the language / languages: English as an attachment in your email.

The manual is 1,92 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of REMKO ML352 DC

REMKO ML352 DC User Manual - German - 32 pages

REMKO ML352 DC User Manual - German - 32 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info