Removal and Vacuumizing
The maintenance or other operations of the refrigeration circuit shall be made as per conventional procedures.
Moreover, the flammability of refrigerant shall also be mainly considered. The following procedures shall be
followed:
Refrigerant clearing;
Pipeline purification with inert gas;
Vacuumizing;
Pipeline purification again with inert gas;
Pipeline cutting or welding. The refrigerant shall be recovered to a proper cylinder. The system shall be
purged with OFN, to ensure safety. The step above may need to be repeated for several times. Compressed air or
oxygen cannot be used for purging.
In the course of purging, OFN shall be charged inside the refrigeration system under vacuum state, to reach
the operating pressure. Afterwards, the OFN shall be discharged to the atmosphere. Finally, the system shall be
vacuumized. The step above shall be repeated until all the refrigerants in the system are cleared. The OFN charged
for the last time shall be discharged to the atmosphere. Afterwards, the system can be welded. The operation
above is necessary in case of pipeline welding.
It shall be guaranteed that no alight fire source is around the outlet of the vacuum pump and the ventilation is
favorable.
Welding
Favorable ventilation must be guaranteed in the maintenance area. After the maintenance machine is subject
to the vacuumizing above, the system refrigerant can be discharged on the outdoor unit side.
Before the outdoor unit is welded, it must be guaranteed that no refrigerant is inside the outdoor unit and the
system refrigerant has been discharged and cleared.
The refrigeration pipelines cannot be cut with a welding gun under any circumstance. The refrigeration
pipelines must be disassembled with a pipe cutter, and the disassembly must be carried out around a ventilation
opening.
Refrigerant Charging Procedures
The following requirements are added as the supplementation of conventional procedures:
During the use of refrigerant charging tools, cross contamination of different refrigerants shall be avoided.
The total length (including the refrigerant pipelines) shall be shortened as much as possible, to reduce the residual
of refrigerant inside;
The cylinders of refrigerant shall be kept upright;
Before refrigerant charging, the refrigeration system shall be earthed;
A label must be pasted on the refrigeration system after refrigerant charging;
Excessive charging is not allowed; the refrigerant shall be charged slowly;
In case system leakage is identified, refrigerant charging is not allowed unless the leak point is plugged;
During refrigerant charging, the charging amount shall be measured with an electronic scale or a spring
scale. The connecting hose between the refrigerant cylinder and the charging equipment shall be relaxed
appropriately, to avoid impact on the measuring accuracy due to stress.
Requirements on storage site of refrigerant
The cylinder of refrigerant shall be placed in a -10~50°C environment with favorable ventilation, and
warning labels shall be pasted;
The maintenance tool in contact with the refrigerant shall be stored and used separately, and the
maintenance tool of different refrigerants cannot be mixed.
Scrapping and Recovery
Scrapping
Before scrapping, the technician shall be completely familiar with the equipment and all its features. The safe
recovery of refrigerant is recommended. In case the refrigerant recovered needs to be reused, before which the
sample of refrigerant and oil shall be analyzed. The power supply required shall be guaranteed before tests.
(1) The equipment and operation shall be well known;
(2) Power supply shall be switched off;
(3) The followings shall be guaranteed before scrapping:
The mechanical equipment shall be convenient for operation on the cylinder of refrigerant (if necessary);
All personal protective equipment is available and being used correctly;
The whole course of recovery shall be guided by qualified personnel;
The recovery equipment and cylinders shall be in line with corresponding standards.
(4) The refrigeration system shall be vacuumized if possible;
9
h
s
i
l
g
n
E
10


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for Haier Zun Tower at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of Haier Zun Tower in the language / languages: English as an attachment in your email.

The manual is 16.71 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info