G3 REQUIREMENTS AND GUIDANCE
Discharge pipe from safety valves
The Building Regulation G3 requires that any discharge from an unvented system is con-
veyed to where it is visible, but will not cause danger to persons in or about the building.
The tundish and discharge pipes should be fi tted in accordance with the requirements and
guidance notes of Building Regulation G3. The G3 Requirements and Guidance sections
3.50 - 3.63 are detailed below.
For discharge pipe arrangements not covered by G3 Guidance advice should be sought
from your local Building Control O cer.
Main characteristics :
Any discharge pipe connected to the pressure relief devices (Expansion Valve and
Temperature/Pressure Relief Valve) must be installed in a continuously downward di-
rection and in a frost free environment.
Water may drip from the discharge pipe of the pressure relief device.
This pipe must be left open to the atmosphere.
The pressure relief device is to be operated regularly to remove lime deposits and to
verify that it is not blocked.
A typical discharge pipe arrangement is shown on next page.
General remarks
Discharge pipe-work D2 can now be a plastic pipe but only pipes that have
been tested to a minimum 11C must be used.
Discharge pipe D2 can now be plumbed into the soil stack but only soil stacks
that can handle temperatures of 99°C or greater should be used.
Extract from “The Building Regulation G3” :
Discharge pipe D1
3.50 Safety devices such as temperature relief valves or combined temperature and pres-
sure and pressure relief valves (see paragraphs 3.13 or 3.18) should discharge either
directly or by way of a manifold via a short length of metal pipe (D1) to a tundish.
3.51 The diameter of discharge pipe (D1) should be not less than the nominal outlet size of
the temperature relief valve.
3.52 Where a manifold is used it should be sized to accept and discharge the total di-
scharge from the discharge pipes connected to it.
3.53 Where valves other than the temperature and pressure relief valve from a single
unvented hot water system discharge by way of the same manifold that is used by the
safety devices, the manifold should be factory fitted as part of the hot water storage
system unit or package.
Tundish
3.54 The tundish should be vertical, located in the same space as the unvented hot water
storage system and be fitted as close as possible to, and lower than, the valve, with
no more than 600mm of pipe between the valve outlet and the tundish.
Note: To comply with the Water Supply (Water Fittings) Regulations, the tundish should in-
corporate a suitable air gap.
UK
SLE - SLE Plus: A1007847 - 661Y2100 • D
Installation
EN
16
16


Need help? Post your question in this forum.

Forumrules


Report abuse

Libble takes abuse of its services very seriously. We're committed to dealing with such abuse according to the laws in your country of residence. When you submit a report, we'll investigate it and take the appropriate action. We'll get back to you only if we require additional details or have more information to share.

Product:

For example, Anti-Semitic content, racist content, or material that could result in a violent physical act.

For example, a credit card number, a personal identification number, or an unlisted home address. Note that email addresses and full names are not considered private information.

Forumrules

To achieve meaningful questions, we apply the following rules:

Register

Register getting emails for ACV Smart E Plus 210 at:


You will receive an email to register for one or both of the options.


Get your user manual by e-mail

Enter your email address to receive the manual of ACV Smart E Plus 210 in the language / languages: English as an attachment in your email.

The manual is 2.14 mb in size.

 

You will receive the manual in your email within minutes. If you have not received an email, then probably have entered the wrong email address or your mailbox is too full. In addition, it may be that your ISP may have a maximum size for emails to receive.

Others manual(s) of ACV Smart E Plus 210

ACV Smart E Plus 210 User Manual - German - 32 pages

ACV Smart E Plus 210 Usermanual and installation guide - Dutch - 32 pages


The manual is sent by email. Check your email

If you have not received an email with the manual within fifteen minutes, it may be that you have a entered a wrong email address or that your ISP has set a maximum size to receive email that is smaller than the size of the manual.

The email address you have provided is not correct.

Please check the email address and correct it.

Your question is posted on this page

Would you like to receive an email when new answers and questions are posted? Please enter your email address.



Info